An eight-kilometre RCC and trimix pavement overlay program on a heavily-trafficked section of the Eastern Expressway, completed in 14 months without full road closure.
The Eastern Expressway serves as a critical freight corridor for the NCR region, carrying in excess of 40,000 PCU daily. By 2023, eight kilometres of pavement between two junctions had deteriorated beyond the point of bituminous patching — rutting, alligator cracking, and base failure were widespread, with rehabilitation intervals dropping to under three years.
Our brief was to specify and execute a permanent overlay system that could withstand the heavy freight loading, complete within the budget envelope, and minimize traffic disruption.
Following a detailed pavement condition assessment, we specified a 100mm RCC base course topped with a 40mm trimix (ironite-rich) wearing course. RCC provides the structural capacity; trimix provides the abrasion and impact resistance needed for heavily-loaded freight traffic.
Execution was staged in 400m sections, with traffic diverted to a single carriageway during each phase. Concrete was supplied from on-site batch plants to maintain consistent quality and pace. Daily compressive-strength testing kept QC rigorous.
The overlay was completed on schedule and within budget. Post-completion monitoring at six months shows negligible rutting under the design freight loading, and the surface is expected to deliver a 15-year service life before any major maintenance intervention.
The success of this project has led to engagement on two additional expressway overlay programs scheduled for 2026.